Germany cleared HUSAR for training and tests ahead of planned 2027 deliveries

Rheinmetall’s September airworthiness announcement and the procurement office’s October delivery update answer different questions about the same German programme.

By Avantika Kapoor, Chief Research Officer and Co-FounderPublished Primary announcement 1 Sept 20262 min read
LinkedIn

Avantika Kapoor is the author of this UXV Searcher analysis. Source and calculation review used AI assistance.

Reported

What changed for HUSAR on 1 September?

Rheinmetall announced that Germany’s military aviation authority had granted provisional airworthiness approval for LUNA NG, which the Bundeswehr calls HUSAR. The decision allows the Bundeswehr to fly independently for training and testing. The company reported roughly 150 flights and 200 hours under civilian operating permissions before this milestone. It said work towards full type certification continued.[S2]

Reported

Why did the forecast delivery year change?

In its 2023 contract amendment, Rheinmetall identified twelve production systems and a separate pilot system. The first production system was then due in the second quarter of 2025. On 23 October 2026, Sicherheit & Verteidigung reported a new statement obtained from the German procurement office, BAAINBw. The office expected deliveries to start in 2027 and finish in 2029. It said evaluation was already under way.[S1] [S3]

UXV Searcher analysis

How should airworthiness progress affect a shipment estimate?

UXV Searcher calculates a two-calendar-year shift in the expected delivery start. The latest source gives a year without a quarter, so the evidence supports a comparison between 2025 and 2027 rather than an exact number of months. The September decision narrows what the buyer still needs to do before it can operate the system, but does not document acceptance of any production unit.

An annual shipment model can move its expected start into 2027 and keep the twelve-system production order intact. The sources give no annual quantity split between 2027 and 2029. Spreading the twelve evenly across those three years would create an analyst scenario, and would need to be identified as such.[S1] [S2] [S3]

Calculations and assumptions

MetricValueFormulaInputsAssumptionsLimitationsSources
Change in expected start year for production-system deliveries2 calendar years2027 revised start year − 2025 original start year
Original schedule: Second quarter of 2025
Revised start: 2027
The amended contract and procurement-office update refer to the same German programme.The updated source gives a year only. Actual delay in months and accepted aircraft quantities remain unreported.[S1] [S3]

Sources

Original reporting is credited to its publisher. The byline covers UXV Searcher's analysis only.

  1. [S1]Original contract amendment and planned first production delivery
    Rheinmetall · Company press release · 28 Sept 2023
    The contractor gives the 2025 first-production-system target, twelve production systems and one pilot system.
  2. [S2]Provisional German military airworthiness approval
    Rheinmetall · Company press release · 1 Sept 2026
    The manufacturer describes the permitted training and test activity and the continuing work on full type certification.
  3. [S3]Procurement office response on first and final deliveries
    Sicherheit & Verteidigung, reporting a BAAINBw spokesperson’s response · 23 Oct 2026
    The publication obtained the delivery schedule directly from Germany’s federal procurement office.

Related in UXV Searcher

Explore the programme evidence

Follow administrative approvals and the dates operators or buyers confirm acceptance.